2002 Feasibility Study:
Meetings From: Frank
L. Hoffman
To: Patricia Outhouse – 518-843-3503 – FAX 843-3537
Date: 24 October 2002
Meeting Attendance:
Frank L. Hoffman, Pres. FLHC
Mary T. Hoffman, V. Pres. FLHC
Patricia Outhouse, Administrator, MMRHCF
Lyle P. Wadsworth, Maintenance Supr.
Robert Nasso, Partner, Rotenberg and Co. CPA
Kay Oliver, Business Office
The purpose of this meeting was to
discuss the financial feasibility of the various options available to
Montgomery Meadows, and how Montgomery County could overcome its loss of
$1,000,000.00 in federal funding over the next four years. The following
items were discussed.
- What would happen to the County’s cash flow if
Montgomery Meadows were sold to a third party?
- The County might be willing to invest in a
significant capital expenditure if they can be assured of a positive
cash flow.
- Can Montgomery Meadows raise their private pay
rate?
- For the purposes of estimating new construction
costs (replacement), use the State cap-rate (+/- $135,000/bed at time
of construction) for new construction and 75% of the cap-rate for
resident care wing additions, as don’t have an architect on board to
draw the plans.
- What would happen if Montgomery Meadows was totally
replaced?
- What would happen if The SNF beds were relocated to
the east side of the present building and the present wings were
converted into an Adult Home.
- For estimating purposes, use $4,000,000.00
($50,000.00/bed for 80 beds) for the cost of renovations and repairs
the existing building to convert the wings to an Adult Home.
- Are there additional funds available for dementia
and behavioral care proposed for the adult or nursing home should
separate units be constructed?
- What effect does rebasing have on the bottom line?
- If we increase the number of private rooms in the
existing SNF, what effect would it have on the bottom line?
- Adult Home private room rate to be $80.00/day plus
special assisting living services.
- SNF addition would be approximately 80,000 sq. ft.
- Existing main floor is 55,000 sq. ft.
- Basement of existing building is approximately
25,000 sq. ft.
Rob will do all the projections on
spreadsheets so that they can be adjusted with various options. He will
bring them on his computer for the next meeting (date to be determined).
There should be separate spreadsheets
for the Nursing Home and the proposed Adult Home. Each spreadsheet
should have lines of columns that shows the effect on the County’s
budget. Show current costs along with projections and the net effect
after construction and renovations.
A formal market study should be done
if the financial feasibility study gives a positive direction.
Montgomery Meadows:
Home Page - Operations -
Programs - Physical Plant -
Financial Analysis
- Market Study - Meetings -
Report
Homepage
About us
Our Philosophy
Construction
Management
Savings
Client
Feedback
Who'd Hire F.L. Hoffman
Scope of
Professional Services
Project
Profiles
Newsletter
Contact Us
Your
comments are welcome
 |